The services are performed on Call Off basis in respect of the Company’s Export PL’s - WREP and SCP Georgian sectors with approx. length of 373km (WREP) and 250km (BTC/SCP) extending from the Azerbaijan/Georgian border to Supsa Terminal (WREP) and the Georgian/Turkish border. Survey and detail design included the following, but not limited to: mechanical, structural, piping, corrosion, welding, electrical, safety/fire, automation, telecommunications, erosion control, landslide mitigation and river crossings enhancement.
Scope of services included provision of senior surveyor, assistants to surveyors and skilled technician.
Scope of services included provision of senior surveyor, assistants to surveyors and skilled technician.
Scope of services includes monitoring topographic survey of SM and DM existing on the landslide sections and faulty zones alongside the AGT Pipelines in Georgia (in Krassovsky 1940 absolute coordinate system). Topographic works are carried out with Total Stations after which new data or Monuments are compared to that of old ones. In total baseline survey of 204 existing monuments should be carried out.
Scope of services includes monitoring topographic survey of new SM and DM on the landslide sections and faulty zones alongside the AGT & WREP Pipelines in Georgia (in Krassovsky 1940 absolute coordinate system). Topographic works are carried out with Total Stations & GPS after which new data or Monuments are compared to that of old ones. In total baseline survey of 204 existing monuments should be carried out.
Supervision for upgrading Km 0 - -Km 27 and Km 27 – Km 54 section of Vaziani-Gombori-Telavi Road.
IDC Ltd acted as a “Local Associate” of MMM Group limited (“Lead Consultant”). Works were conducted in accordance of FIDIC guidelines and included supervision of: road rehabilitation, arrangement of bridges, gabions, retaining walls, water drainage and reinforced concrete channels.
Topographical and geotechnical surveys were performed. Reinforced concrete foundations for STP units (RBC Unit, Twin Effluent Pump Station, UV Chamber and Mag Flow meter), concrete surroundings and pipelines from STP facilities to r. Supsa were designed in accordance with provided dimensions. Layout schemes for STP facilities were determined.