    ორშაბათი, 30 ოქტომბერი 2017 19:48

    Tsalka Internal Roads Rehabilitation (9.6km length)

    Assessment of the road, development of road plans and road cover structure types.
    Supervision of construction services, such as - cleaning/reinstating existing concrete ditches and pipes, leveling road bed, reinstating the damaged asphalt cover, removing deformed sub layer and damaged and cracked asphalt, arranging of asphalt layer, repairing concrete ditches and culverts, arranging new culverts, marking the cover etc.

    Additional Info

    • Client Name BP/BTC Co
    • Work Type Feasibility Study, Construction
    • Start თებერვალი 2005
    • Completion დეკემბერი 2005
    • Location Georgia
    Published in Projects
    ორშაბათი, 30 ოქტომბერი 2017 19:45

    Bakuriani Central Road (1.29km length) and Bypass Road (3km length) Rehabilitation

    Rehabilitation measures revision.
    Project planning and scheduling, monitoring and reporting of physical and financial progress, quality assurance, HSE assurance.
    Supervision of construction services, such as - cleaning/reinstating existing concrete ditches, arranging r/c roadside ditches, reinstating the damaged asphalt cover, removing deformed cover and foundation, arranging of asphalt layer, replacement of bridge cover and water culvert pipes, arranging road shoulders etc.

    Additional Info

    • Client Name BP/BTC Co
    • Work Type Feasibility Study, Construction
    • Start თებერვალი 2005
    • Completion აგვისტო 2005
    • Location Georgia
    Published in Projects
    ორშაბათი, 30 ოქტომბერი 2017 19:42

    Lemshveniera Road Rehabilitation

    Assessment of the road, development of road plans and road cover structure types.
    Project planning and scheduling, monitoring and reporting of physical and financial progress, quality assurance, HSE assurance.
    Supervision of construction services, such as - cleaning/reinstating existing concrete ditches, earth and gravelling works, arranging water culvert pipes, reinstating the damaged asphalt cover, removing damaged and cracked asphalt, arranging of asphalt lower and upper layers, using geotextile Terram 1500 to strengthen road foundation at some specific sections, arranging road shoulders and parapets.

    Additional Info

    • Client Name BP/BTC Co
    • Work Type Feasibility Study, Construction
    • Start თებერვალი 2005
    • Completion ივლისი 2005
    • Location Georgia
    Published in Projects
    ორშაბათი, 30 ოქტომბერი 2017 19:37

    Rehabilitation of Iagluja Landfill Access Road (0,4km length)

    Assessment of the road, development of road plans and road cover structure types.
    Project planning and scheduling, monitoring and reporting of physical and financial progress, quality assurance, HSE assurance.
    Supervision of construction services, such as - cleaning the existing road from extra soil, profiling ground layer and road surface, restoring the road base with sand/gravel mix, arranging road cover with sand/gravel mix/asphalt concrete, arranging stone barriers and road signs.

    Additional Info

    • Client Name BP/BTC Co
    • Work Type Feasibility Study, Construction
    • Start მარტი 2005
    • Completion აპრილი 2005
    • Location Georgia
    Published in Projects
    ორშაბათი, 30 ოქტომბერი 2017 19:34

    Ten Bridges Current Structural Assessment in Tbilisi

    Bridges technical condition visual assessment, concrete grade and cracks width determination, bridges bearing structures conditions assessment, rehabilitation measures recommendations development (e.g. special testing, detailed design, and rehabilitation works types.)

    Additional Info

    • Client Name Tbilisi City Council Maintenance Department
    • Work Type Structural Study
    • Start მარტი 2005
    • Completion აპრილი 2005
    • Location Georgia
    Published in Projects
    ორშაბათი, 30 ოქტომბერი 2017 19:32

    Structural Survey of WREP Exports/PU Warehouse

    Preparation of plans of existing facility, assessment/provision of detailed scope of works for existing lifts, determination of floor loading per square meter, calculation of the warehouse for 8 point seismic load using program “Lira”

    Additional Info

    • Client Name BP/BTC Co
    • Work Type Structural Study
    • Start მარტი 2005
    • Completion მარტი 2005
    • Location Georgia
    Published in Projects
    ორშაბათი, 30 ოქტომბერი 2017 19:12

    Tetritskaro Entrance Road (3,0 km length) and Bypass Road (2,0km Length) Rehabilitation

    Visual assessment of the road, development of road plans and road cover structure types.
    Project planning and scheduling, monitoring and reporting of physical and financial progress, quality assurance, HSE assurance.
    Supervision of construction services, such as - cleaning/reinstating existing concrete ditches, earth and gravelling works, arranging water culvert pipes, reinstating the damaged asphalt cover, removing damaged and cracked asphalt, arranging of asphalt layer, arranging road shoulders and parapets etc.

    Additional Info

    • Client Name BP/BTC Co
    • Work Type Feasibility Study, Construction
    • Start თებერვალი 2005
    • Completion ოქტომბერი 2005
    • Location Georgia
    Published in Projects
    ორშაბათი, 30 ოქტომბერი 2017 19:07

    Detailed Survey of Overhead Power Lines Along the BTC Pipeline ROW

    Study of all power lines and cables, their ownership, voltage, KP of power line crossing, GPS grid reference, height of power lines across the ROW.

    Additional Info

    • Client Name BP/BTC Co
    • Work Type Field Survey, Data Development
    • Start თებერვალი 2005
    • Completion მარტი 2005
    • Location Georgia
    Published in Projects
    ორშაბათი, 30 ოქტომბერი 2017 19:04

    Maintenance Works at Rustavi Pipe Yard

    Installation of Electrical Lighting, Installation and Dismantling of a Portable Toilet, Rent of Generator, Security Shack, Changing Room

    Additional Info

    • Client Name Seacor Environmental Services International
    • Work Type Maintenance
    • Start თებერვალი 2005
    • Completion მაისი 2005
    • Location Georgia
    Published in Projects
    ორშაბათი, 30 ოქტომბერი 2017 19:03

    Installation of Monitoring Boreholes at HDD Site

    Installation of six monitoring boreholes and piezometers for continuous monitoring of underground water levels on river Mtkvari.

    Additional Info

    • Client Name BP/BTC Co
    • Work Type Field Survey
    • Start თებერვალი 2005
    • Completion მარტი 2005
    • Location Georgia
    Published in Projects