Gardabani mazut storage site inspection, condition survey of underground and above ground mazut storage tanks, mazut low and high-pressure heaters, electrical network, mazut discharge facilities, pumps, etc.
Provide and maintain access roads (total length approximately 25km) to a set number of Block and Check Valves sites on the western section in conjunction with maintaining life services and support to the physical security assets that are deployed to the Block and Check Valves.
Architectural design of structure surfaces. Design of generators or heavy capacity batteries storage area in structures’ lower bay. Design of bank revetments and river-bed landscape due to environmental fitness. Hydrological recalculation of cross hydraulic structures in case of lack of orifices.
Topographic and geotechnical survey of 9km long Tori access road, hydrological surveys, design of gravel road structure and artificial structures (design of three small bridges and 32 culverts).
Survey of structures and all associated bearing elements, define of construction requirements for ventilators installation, cables tracking on the wall, design of strengthening r/c slab and butt fitting, design of support frame, structures calculation from seismic impact point
Geodetic survey and geotechnical visual check was performed on PSG1 and PSG2 area. Design of reinforced concrete foundation for hazardous and non-hazardous landfills. Design of structural part and foundation of wheel barrow parking area structure.
Project planning and scheduling, monitoring and reporting of physical and financial progress, quality assurance, and HSE assurance.
Supervision of construction services such as - graveling two yards with total area of 928km2 and fencing with barbed wire. Constructing two office modules, changing closet for personnel, catering module, toilets, and security booth. Concreting reinforced concrete slabs due to fuel tank and diesel generator placement. Installation of steel containers for material and tools storage. Installation of water pump; tracking power supply, water supply and se3wage systems. Arrangement of 1200m long and 5m wide landfill access gravel road.
Prepare plans of the existing facility. Determination of floor loading per square meter on the first floor of warehouse
Calculation the warehouse for 8 point seismic load in case the walls on the ground and first floors are demolished.
Determination of repair works scopes including concrete, carpentry, plastering, electrical and etc works.
Project planning and scheduling, monitoring and reporting of physical and financial progress, quality assurance, and HSE assurance.
Supervision of construction services such as - cleaning and partially profiling road with area of 1200km2, arranging soil and reinforced concrete ditches; placing steel culverts at the yard entrances and road crossings; arranging reinforced concrete inlet and storm wells etc.
Performing reconnaissance works of North-South Gas Main passing through Georgia together with GGIC personnel. Due to planning survey and design work development producing survey and design packages, determining calendar schedule and estimate of survey and design works cost. Survey and design works include four main components: gas pipeline, geotechnical hazards, gas pipeline infrastructure, and environmental protection.
Drilling geotechnical boreholes, conducting laboratory analysis of soil samples. Possibilities to install and conduct various types of communications like low and high voltage power transmission lines, water supply system were determined. Relevant report development.
Design and arrangement of temporary dams at 6 small stream crossings in Bakuriani Districts, in order to avoid spread of potentially oil contaminated water. Dams represent sandbags and in order to ensure rigidity of the dam and undertake potential pressurization of water, they are placed in accordance to some specific rule and are fixed in with reinforcement.
Drilling boreholes of various depths (10-30m) in Tabatskuri and Bakuriani districts. Installation of piezometers to carry out monitoring of underground waters and contamination levels.
Assessment of the road, development of road plans and road cover structure types.
Project planning and scheduling, monitoring and reporting of physical and financial progress, quality assurance, HSE assurance supervision of construction services.
Sakire village roads have very high gradients and road width is narrowed due to local fences. Taking into consideration this particularity, road reinstatement technology was processed and road works comprised of Profiling/leveling, using coarse grained river gravel for road foundation, arrangement of culverts and ditches.
Assessment of the road, development of road plans and road cover structure types.
Supervision of construction services, such as - cleaning/reinstating existing concrete ditches and pipes, leveling road bed, reinstating the damaged asphalt cover, removing deformed sub layer and damaged and cracked asphalt, arranging of asphalt layer, repairing concrete ditches and culverts, arranging new culverts, marking the cover etc.
Rehabilitation measures revision.
Project planning and scheduling, monitoring and reporting of physical and financial progress, quality assurance, HSE assurance.
Supervision of construction services, such as - cleaning/reinstating existing concrete ditches, arranging r/c roadside ditches, reinstating the damaged asphalt cover, removing deformed cover and foundation, arranging of asphalt layer, replacement of bridge cover and water culvert pipes, arranging road shoulders etc.
Assessment of the road, development of road plans and road cover structure types.
Project planning and scheduling, monitoring and reporting of physical and financial progress, quality assurance, HSE assurance.
Supervision of construction services, such as - cleaning/reinstating existing concrete ditches, earth and gravelling works, arranging water culvert pipes, reinstating the damaged asphalt cover, removing damaged and cracked asphalt, arranging of asphalt lower and upper layers, using geotextile Terram 1500 to strengthen road foundation at some specific sections, arranging road shoulders and parapets.
Assessment of the road, development of road plans and road cover structure types.
Project planning and scheduling, monitoring and reporting of physical and financial progress, quality assurance, HSE assurance.
Supervision of construction services, such as - cleaning the existing road from extra soil, profiling ground layer and road surface, restoring the road base with sand/gravel mix, arranging road cover with sand/gravel mix/asphalt concrete, arranging stone barriers and road signs.
Bridges technical condition visual assessment, concrete grade and cracks width determination, bridges bearing structures conditions assessment, rehabilitation measures recommendations development (e.g. special testing, detailed design, and rehabilitation works types.)
Preparation of plans of existing facility, assessment/provision of detailed scope of works for existing lifts, determination of floor loading per square meter, calculation of the warehouse for 8 point seismic load using program “Lira”
Visual assessment of the road, development of road plans and road cover structure types.
Project planning and scheduling, monitoring and reporting of physical and financial progress, quality assurance, HSE assurance.
Supervision of construction services, such as - cleaning/reinstating existing concrete ditches, earth and gravelling works, arranging water culvert pipes, reinstating the damaged asphalt cover, removing damaged and cracked asphalt, arranging of asphalt layer, arranging road shoulders and parapets etc.
Study of all power lines and cables, their ownership, voltage, KP of power line crossing, GPS grid reference, height of power lines across the ROW.
Installation of Electrical Lighting, Installation and Dismantling of a Portable Toilet, Rent of Generator, Security Shack, Changing Room
Installation of six monitoring boreholes and piezometers for continuous monitoring of underground water levels on river Mtkvari.
Topographic survey of Kura river downstream of crossing site at KP 223 using Total Station equipment for design of village protection works.
Topographic survey of Kura West River crossing, Obtaining hydrological data for Kura East River crossing.
Drilling boreholes and arrangement of piezometers for underground water encountering and water level monitoring purposes. Taking water and soil samples and carry out lab analysis, arrangement of monuments for monitoring the land-slide area.
Spatial modelling of building carcass on cross and long seismic forces using program Lira, determination of the strength of earthquake the existing building shall resist, design of constructive measures to increase the building seismicity, calculation of the floor of the building on loads caused by transport movement.
Hydrological survey, hydraulic calculation of structures, structures bearing constructions design, access road design, and construction works scopes and schedules determination, construction works cost estimation.
Topographic survey of containment site at Tsikhisjvari – Oshora 2 and Iagluja landfill.
Drilling of 19 monitoring boreholes in Bakuriani district and arrangement of piezometers for continuous monitoring of underground waters and potential contamination levels.
Geotechnical investigation at six different sites. Drilling 135 m boreholes, conducting Lab tests for determination of mechanical, physical and chemical properties of soils and ground waters.
Test digs of foundations to assess the quality and strength of floors, test to determine the grade of the bitumen used on foundations surface, check joint quality between bearing precast structures, determine concrete grade of precast structures, check roof of buildings.
Trench line safety barrier construction, damage repair to essential services or structures, area clean-up and row clean-up, Akhaltsikhe and Tsalka Camps maintenance works, BV17, BV18, BV21 and BV22 maintenance works
Visual assessment of the road, development of road plans and road cover structure types.
Project planning and scheduling, monitoring and reporting of physical and financial progress, quality assurance, HSE assurance.
Supervision of construction services, such as - profiling/leveling the existing ground road sections and arrangement of sand-gravel layer, road side ditches and steel water pipes at yard entrances and road crossings.
Technical assessment of Tbilsresi Power Units #3,4 and 8 and determination of rehabilitation work scopes and costs.
Design and survey of Bakuriani Central (3,7 km) and Bypass Roads (3,0 km), topographic survey of both roads, design of road long and cross sections, determination of road cover structure types, development of detail drawings necessary for rehabilitation of bridges and culverts, design of concrete ditches and definition of rehabilitation work scopes and costs.
Project planning and scheduling, monitoring and reporting of physical and financial progress, quality assurance, HSE assurance.
Supervision of construction services, such as - rehabilitation of asphalt road (1,31 km long) and gravel road (1,1 km long) in Bakuriani, placement of reinforced concrete ditches and triangular concrete chutes on the asphalt roads and the repair of two bridge overpasses.
Field test of the bridges over r. Mtkvari at village Atskuri and village Agara of Akhaltsikhe region. Loads Calculation. Recommendations Development.
Design and construction works for water supply system of Bakuriani region, namely: geotechnical and survey works on route, determination of optimal route of the pipeline (3.5km), water supply system hydraulic report, including pipeline testing design; development of the design for headwork facility, water supply system construction, arrangement of headwork facility, one aerial crossing of river Tskhratskaro, one crossing of BTC pipeline route; installation of two reinforced concrete control wells and two reinforced concrete water supply regulation wells, testing of water supply system after construction, production of as-built documentation etc.
Obtain all the documentation concerning earthquake/tremors that have occurred in Tbilisi Georgia, and their frequency and magnitude over last 100yrs. Complete test digs of the foundations to access the quality, strength and floor weight loading per square meter, Complete test to determine the grade of bitumen used on the foundation surface and assess stability, determine the reinforcement precast elements of entire floor foundations.
Monitoring and reporting of physical and financial progress, quality assurance, HSE assurance.
Supervision of construction services, such as - construction of access road, site grading and leveling, construction of pre-designed concrete slab, construction of sewage disposal septic tank and water distribution system, installation of security fences and gates, arrangement of 250mm crushed gravel layer, installation of perimeter lighting, erection of pre-engineered steel building.
Survey of overhead obstacles and bridge class loads determination for the following routes: Khashuri to Batumi state highway, Batumi to Poti state highway and Poti to Zestafoni to Chiatura to Gori state highway.
Assess integrity of site retaining wall, carry out topographical survey, drill boreholes to determine geotechnical properties of the soil and carry out laboratory testing.
Visual assessment of the road, development of road plans and road cover structure types.
Project planning and scheduling, monitoring and reporting of physical and financial progress, quality assurance, HSE assurance.
Supervision of construction services, such as - Profiling/leveling the existing ground road sections and arrangement of sand-gravel layer, road side ditches and steel water pipes at yard entrances and road crossings, pit-patching of the sections with asphalt concrete cover.
Preliminary assessment of roads condition, rehabilitation work scope determination and preliminary cost estimation.
Survey of overhead obstacles for the following routes: Red bridge/ Azerbaijan border crossing to Tbilisi transit route, Tbilisi transit route and Tbilisi transit route to Rustavi receiving yard to PSG1, Rustavi receiving yard to Marneuli to Tetritskaro to PSG2, PSG2 to Tsalka via all-weather access track, Khashuri to Borjomi to Akhaltsikhe to Vale to Turkish border Crossing and Borjomi to Bakuriani to Tsikhisjvari.
Topographical Survey of Reed Bed Area in 1:500 scales. Relevant drawings development
Assisting with procurement of construction, supervision of construction services, project planning and scheduling, monitoring and reporting of physical and financial progress, quality assurance, and HSE assurance.
Removal of damaged road base, paving geotextile membrane and arranging asphalt concrete upper layer starting from road cover base afterwards, arrangement of ditches, shoulders and road markings.
Topographical survey in the Sakire area, stream cross-section, slope and sediment surveys and collection of hydrological data.
Design of road cover, development of bridges and water pipes rehabilitation project, Environmental Impact Assessment, processing construction organization, preparation of relevant documentation for construction.
It has to be noted that there are three landslide hazard segments on Partskhisi-Manglisi segment, for which anti erosion structures – Gabion Retaining walls, Gabion Controls dams and Rip-Rap Channels were arranged
Spill bases sites survey works in Borjomi and Tsalka (scale 1:500), drilling geotechnical boreholes, laboratory analysis of soil samples, and preparation of relevant reports.