მოძებნე პროექტი

    ძებნის პარამეტრები

    • საძიებო სიტყვა
    • წელი
    • კლიენტი

    Projects

    Marneuli-Jandara and Tetritskaro-Tsalka Motor Roads Rehabilitation Costs Preliminary Assessment

    Reconnaissance and design works. Reconnaissance works comprised of technical assessment of Marneuli-Jandara (61,4 km) and Tetritskaro-Tsalka (31,22 km) Roads and artificial structures located on these roads and Geotechnical visual inspection of the entire route.
    Design Works. Definition of rehabilitation work scopes on the basis of inspections and technical assessments of existing roads; development of road cover structures and rehabilitation work costs.

    Additional Info

    • Client Name Spiecapag/Petrofac JV
    • Work Type Feasibility Study
    • Start ნოემბერი 2003
    • Completion დეკემბერი 2003
    • Location Georgia

    Engineering and Quantity Surveying Works for BTC Pipeline 9 River Crossings

    Determination of pipeline position on longitudinal sections, visual evaluation of soil, determination of cross-section configuration issuing relevant recommendations, determination of excavation work scopes.

    Additional Info

    • Client Name Spiecapag/Petrofac JV
    • Work Type Feasibility Study
    • Start ნოემბერი 2003
    • Completion დეკემბერი 2003
    • Location Georgia

    Tsalka District Water Infrastructure Project

    Design and construction works for water supply of 6 villages of Tsalka district, namely: geotechnical and survey works on route, determination of optimal route of the pipeline (24km), water supply system hydraulic report, including pipeline testing design; Development of the rehabilitation design for headwork facilities, chlorine treatment facilities, existing two reservoirs, international and local supply with construction materials; design of two new capacity reservoirs construction, water supply system construction; two new 100kb/m reservoir, headwork facility and chlorine treatment facility, testing of water supply system after construction completion, production of as-built documentation etc.
    Assisting with procurement of construction, supervision of construction services, project planning and scheduling, monitoring and reporting of physical and financial progress, quality assurance, and HSE assurance.

    Additional Info

    • Client Name BP/BTC Co
    • Work Type Detail design, Project Management
    • Start ნოემბერი 2003
    • Completion სექტემბერი 2004
    • Location Georgia

    Providing an Expert Service on “Effective Usage of Energy Resources by Communities an Improvement of Access to Energy Sources”

    Preparation of a summary detailing the existing technology on effective usage of the energy and alternative energy resources, development of charts of technology, providing suggestions on development of brochures and other demonstration materials.

    Additional Info

    • Client Name Umid HSSC
    • Work Type Feasibility Study
    • Start ოქტომბერი 2003
    • Completion დეკემბერი 2003
    • Location Georgia

    Call off to Provide Minor Works

    Dig trench of approximate 500m at designated location. Purchase and delivery 150mm diameter steel pipes in V. Sakuneti, Bakuriani District
    Constructing wooden and plank wall due to muffling noise from 22kw generator located in Tsalka town area.
    Manufacturing special equipment for pipeline out-of-roundness measurement.
    Delivery of portable water to Tsemi population by water tanker.
    Repair of water supply pipeline in Tsikhisjvari village, Bakuriani district.
    20cm thick sand-gravel mix was compacted along 3000m2 area was arranged at Rustavi PipeYard
    Outer and internal refurbishment works of Darakov village community hall in Tsalka district.
    Replacement of glasses in the schools in 2 villages of Tsalka region and restoration of some very damaged road segments

    Additional Info

    • Client Name BP/BTC Co
    • Work Type Minor works provision
    • Start სექტემბერი 2003
    • Completion დეკემბერი 2003
    • Location Georgia

    Explosives Factory in Marneuli District – Environmental Impact Assessment

    Survey of ecological conditions of the area, environmental impact on topsoil, atmosphere and ground waters while factory construction – operation-takedown inclusive of potential risk assessments and mitigation measures development

    Additional Info

    • Client Name Geo Nitro Ltd
    • Work Type EIA
    • Start სექტემბერი 2003
    • Completion ნოემბერი 2003
    • Location Georgia

    Provision of Stream Cross-Section and Topographic Survey “Scope-1”

    Topographic survey, cross-section survey, sediment sampling and grain size analysis, determination of maximum flow rates, processing of field data and preparation of deliverables for rivers Ktsia, Algeti and Gumbati and five stream crossings with BTC in Borjomi-Bakuriani region.

    Additional Info

    • Client Name BP/BTC Co
    • Work Type Field Survey, Data Development
    • Start აგვისტო 2003
    • Completion სექტემბერი 2003
    • Location Georgia

    Provision of River Crossing Surveys

    Hydrological survey, river cross-section surveys and river sediment sampling of the six rivers in Akhaltsikhe area.

    Additional Info

    • Client Name BP/BTC Co
    • Work Type Field Survey, Data Development
    • Start აგვისტო 2003
    • Completion სექტემბერი 2003
    • Location Georgia

    Provision of Stream Cross-Section and Topographic Survey “Scope-2”

    Topographic survey, cross-section survey, sediment sampling and grain size analysis, determination of maximum flow rates, processing of field data and preparation of deliverables for rivers Ktsia, Algeti and Gumbati and five stream crossings with BTC in Borjomi-Bakuriani region.

    Additional Info

    • Client Name BP/BTC Co
    • Work Type Field Survey, Data Development
    • Start ივნისი 2003
    • Completion ივლისი 2003
    • Location Georgia

    Access Roads Rehabilitation Design in Bakuriani Region for Baku-Tbilisi-Ceyhan (BTC) Pipeline Construction Project (60 km total length)

    Design of rehabilitation measures for Bakuriani-Tetritskaro Pass, Bakuriani-Tsikhisjvari, Dviri-Sakire and Borjomi-Bakuriani segments and geotechnical field works, visual geotechnical assessment during this period; development of road cover structures, road plans, long and cross-section profiles; re-design of small radius and narrow section of roads, bridge and pipe rehabilitation works, retaining walls in landslide area and galley places etc.

    Additional Info

    • Client Name Spiecapag/Petrofac JV
    • Work Type Field Survey, Design
    • Start ივნისი 2003
    • Completion ივლისი 2003
    • Location Georgia

    Survey Works as Part of the Baku-Tbilisi-Ceyhan (BTC) Geohazards Investigation

    Line and point surveys using total station equipment at the Minadze, Tiseli, Sakire and Kodiana sites in Bakuriani District

    Additional Info

    • Client Name URS D&M
    • Work Type Field Survey
    • Start მაისი 2003
    • Completion ივნისი 2003
    • Location Georgia

    WREP Rustavi Fault Crossing Engineering Measures Development (KP479)

    Design works in order to improve pipeline operable conditions at KP479,7 from Baku tectonic fault crossing of Georgian Section of WREP.

    Design works: F5,3 ha field topographic survey, geotechnical and laboratory works, pipeline burial depth determination, desktop processing, development of the design to provide re-grading of soil cover on the 200m section of the pipeline also to enable effective drainage of rainwater by rip-rap channels; determination of relevant ground works scopes; reduce soil cover to 0.9m over the pipeline in order to improve pipe working under seismic loads

    Additional Info

    • Client Name Georgian Pipeline Company
    • Work Type Detail design, Field Survey
    • Start მარტი 2003
    • Completion მარტი 2003
    • Location Georgia

    Design of Soil Cover Increasing on Old Sections of WREP (KP44 – KP50)

    Topographic survey works and office data processing, determination of several alternative options for ground work scopes needed to increase ground layer thickness above pipe (by 60, 70 or 80 cm); development of proposed work scopes list and design of culvert to ensure normal operable conditions of the earth road at KP46+179.

    Additional Info

    • Client Name Georgian Pipeline Company
    • Work Type Detail design, Field Survey
    • Start მარტი 2003
    • Completion მარტი 2003
    • Location Georgia
    გვერდი 4 სულ 4
    © 2002-2020 IDC Ltd. All Rights Reserved. Developed By GT-studio

    ძებნა