Preparation of the Design and Bidding Documents for the First Year Contracts.
Client
The State Department of Roads of Georgia/WB Transport Reform and Rehabilitation Center
Work Type
Detail Design
Location
Georgia
Project Status
Completed
Start Date
2004-02-27
End Date
2004-05-27
Preparation of the Design and Bidding Documents for the First Year Contracts.
Design of road cover, development of bridges and water pipes rehabilitation project, Environmental Impact Assessment, processing construction organization, preparation of relevant documentation for construction.It has to be noted that there are three landslide hazard segments on Partskhisi-Manglisi segment, for which anti erosion structures – Gabion Retaining walls, Gabion Controls dams and Rip-Rap Channels were arranged