Investigation Design Construction

    Find Project

    Filter by:

    • Search
    • Year
    • Client Name

    Projects

    Provision of Civil and Structural Construction Services for BP Georgia

    Civil works - temporary works, site clearance, site set-up, transportation (including handling and lifting) of materials and equipment, in-situ concrete, pre-cast concrete, piling, excavations, shoring, fencing, man-holes, pits/covered tanks, sewer and water main renovation and ancillary works, pipelines and pipework (on ground, in trenches), roads and pavings, earthworks, ground investigation, building works, reinstatement, river crossings works, drainage works, dewatering, cable ducting (below ground), procurement, supply and delivery of materials and consumables, painting , waterproofing, inspection and testing, removal of excess and waste materials from the worksite upon completion of the work., preparation of as-built and materials traceability drawings, weld record/NDE drawings and the compilation and presentation of certification packages.

    Structural works - structural fabrication, pre-fabrication, transportation (including handling and lifting) of pre-fabricated assemblies, materials and equipment, structural construction, procurement, supply and delivery of consumables, inspection and testing, removal of excess and waste materials from the worksite upon completion of the work, preparation of as-built and materials traceability drawings, weld record/NDE drawings and the compilation and presentation of certification packages.

    The Project is on Call-off basis.

    Project Details

    • Client Name BP Exploration (Caspian Sea) Ltd. - Georgia
    • Work Type Provision of Civil Services for BTC/SCP and WREP in Georgia
    • Start Thursday, 01 February 2018
    • Completion Sunday, 28 February 2021
    • Location Georgia

    Supsa Camp Water Pipework Replacement

    Execution of design works for Supsa Camp of Baku-Supsa oil pipeline. Basing on the design, the existing pipework was replaced at external area and inside of Supsa Camp. The work included replacement of hot water, cold water and heating pipelines. In total, 630 m internal network pipes and 940 m external network pipes were replaced. Also, existing diesel-powered tank was replaced with new electrical water heater, equipped with softener and pumps.

    Project Details

    • Client Name BP Exploration (Caspian Sea) Ltd. - Georgia
    • Work Type Design, Construction
    • Start Wednesday, 01 November 2017
    • Completion Wednesday, 28 February 2018
    • Location Georgia

    Rustavi-Jandara Road Rehabilitation, Section 2 (6,0 km length)

    Project planning and scheduling, monitoring and reporting of physical and financial progress, quality assurance, HSE assurance, procurement. Carry out construction works such as - excavation of damaged asphalt concrete, constructing of road base with sand-crushed stone material, arrangement layers of pavement from coarse and fine grained asphalt concrete mix.

    Project Details

    • Client Name BP Exploration (Caspian Sea) Ltd. - Georgia
    • Work Type Construction
    • Start Wednesday, 01 November 2017
    • Completion Wednesday, 28 February 2018
    • Location Georgia

    Rustavi-Jandara Road Rehabilitation (4,34 km length)

    Project planning and scheduling, monitoring and reporting of physical and financial progress, quality assurance, HSE assurance, procurement. Carry out construction works, such as - cold milling of damaged asphalt concrete, repair of potholes in the existing asphalt concrete, constructing of road base with sand-crushed stone material, arrangement layers of pavement from coarse and fine grained hot asphalt concrete mix, constructing the shoulders from sand-crushed stone material, road marking.

    Project Details

    • Client Name BP Exploration (Caspian Sea) Ltd. - Georgia
    • Work Type Construction
    • Start Monday, 01 May 2017
    • Completion Saturday, 30 September 2017
    • Location Georgia

    PSG1 Accommodation Geotechnical Investigation

    4 boreholes with a total length of 32 m were drilled within an area of 10880 sq. m., 4 CBR tests were conducted, laboratory tests of physical-mechanical and chemical properties of the soil samples taken from the boreholes were conducted.

    Project Details

    • Client Name WorleyParsons Europe Ltd
    • Work Type Geotechnical Survey
    • Start Wednesday, 01 March 2017
    • Completion Sunday, 30 April 2017
    • Location Georgia

    Construction/renovation works at PSG2 facility

    Project planning and scheduling, procurement of materials, monitoring and reporting of physical and financial progress, quality assurance, HSE assurance, carry out of construction/renovation activities, such as modification of existing ventilation system network, removal of existing flooring and arrangement of new one using ceramic tiles, installation of sewerage and water supply networks, wall painting, installation of wooden and steel doors, installation of Armstrong ceiling.

    Project Details

    • Client Name WorleyParsons Europe Ltd
    • Work Type Construction, Renovation
    • Start Saturday, 01 October 2016
    • Completion Saturday, 31 December 2016
    • Location Georgia

    Ristavi-Jandara Road Design

    Topographical Survey of the existing road with a length of approximately 4,5 km and a width of 9,5m (inclusive 1,5m shoulders on each side). Installation of 9 permanent benchmarks, within this defined corridor survey all surface and overhead features and CAT scan to determine the locations of underground facilities. Develop road design drawings providing the horizontal alignment, cross – sections and profile. Adopt the existing road vertical and horizontal alignments wherever possible. Provision BOQ for construction/rehabilitation works, report development.

    Project Details

    • Client Name BP Exploration (Caspian Sea) Ltd. - Georgia
    • Work Type Design, Survey
    • Start Monday, 01 August 2016
    • Completion Wednesday, 30 November 2016
    • Location Georgia

    MX77 Access Road Construction

    Project planning and scheduling, procurement of materials, monitoring and reporting of physical and financial progress, quality assurance, HSE assurance, carry out of construction activities, such as stripping and stockpiling the topsoil, construction of levelling layer and road structure using sand/gravel and crushed rock, installation of 500 mm diameter culverts using corrugated plastic pipes, arrangement of ditches, installation of concrete slabs at the pipeline crossings. Road length is 2 050 m.

    Project Details

    • Client Name Saipem Contracting Netherlands BV Georgia Branch
    • Work Type Construction
    • Start Friday, 01 July 2016
    • Completion Monday, 31 October 2016
    • Location Georgia

    Topographical Survey Georgia – SCPX Project

    Detailed survey of pipeline route (63 km), existing benchmarks checking, new primary control points establishment, staking of pipeline route axis, survey of railway, roads, underground and above ground communications crossings, survey of plants at MX40/41, MX77, MX81, delivery of maps, drawings, reports.

    Project Details

    • Client Name Saipem Contracting Netherlands BV Georgia Branch
    • Work Type Survey
    • Start Saturday, 01 August 2015
    • Completion Thursday, 31 August 2017
    • Location Georgia

    CSG2 Road Camp – Provision of Treated waste water drainage ditch

    Modification/upgrade of existing 1000 m long drainage ditch along Millennium Road with positioning of the mass concrete weirs.

    Project Details

    • Client Name BP Exploration (Caspian Sea) Ltd. - Georgia
    • Work Type Construction
    • Start Wednesday, 01 October 2014
    • Completion Sunday, 30 November 2014
    • Location Georgia

    Topographical and geotechnical investigations at Rustavi Pipe Load Area

    Topographical survey of approximate 7-hectare area, execution of CBR testing, issue of respective topographical drawings and geotechnical report.

    Project Details

    • Client Name Saipem/Azfen JV
    • Work Type Survey
    • Start Wednesday, 01 October 2014
    • Completion Sunday, 30 November 2014
    • Location Georgia

    Liakhvi River Rehabilitation

    Design of rehabilitation measures of Liakhvi river crossing, site preparation, 68  868 m3 soil excavation, 15  000 m2 geotextile filter layer installation, 19  043 m3 riprap installation to armour the river banks, 21  320 m3 riprap installation for arrangement of threshold across the river bed, 24  290 m3 excavated soil backfill and installation of fill, installation of dam with 2  810 m3 local sand/gravel, distribution of 40  374 m3 surplus soil within the river bed and at riverside slopes, supply and delivery of 34  460 m3 of stones, site reinstatement, preparation of as-built drawings.

    Project Details

    • Client Name BP Exploration (Caspian Sea) Ltd. - Georgia
    • Work Type Design, Construction
    • Start Tuesday, 01 July 2014
    • Completion Saturday, 28 February 2015
    • Location Georgia

    Small Project Design in Georgia

    Detail Design for all disciplines required for the Services including, but not limited to: mechanical, structural, piping, stress, process, corrosion, welding, instrumentation, electrical, safety/fire, automation, telecommunications, materials, package/vendor, civil including erosion control, landslide mitigation and river crossings enhancement works engineering. The Project is on Call-off basis.

    Project Details

    • Client Name BP Exploration (Caspian Sea) Ltd. - Georgia
    • Work Type Design, Survey
    • Start Tuesday, 01 July 2014
    • Completion Wednesday, 31 July 2019
    • Location Georgia

    Provision of River Crossing Enhancement Works

    Erosion control and reinstatement works at River Crossings, which includes but not limited to river bank and bed reinforcement works with Riprap, Maccaferri gabions, concrete structures and etc; Reinstatement and recovery of the preconstruction vegetation and etc. The Project is on Call-off basis.

    Project Details

    • Client Name BP Exploration (Caspian Sea) Ltd. - Georgia
    • Work Type Construction
    • Start Tuesday, 01 July 2014
    • Completion Wednesday, 31 January 2018
    • Location Georgia

    Civil and General Project Services

    Provide Company with construction, civil engineering, design, surveying and general Project services as per detailed Scope of Work described in Call-Off’s, which shall be issued by Company time by time. The works performed / to be performed at any site/s required by Company inclusive of, but not limited to, pipeline river and canal crossings, access roads, pipeline over-ground installations etc.

    Project Details

    • Client Name BP Exploration (Caspian Sea) Ltd. - Georgia
    • Work Type Design, Construction, Survey
    • Start Sunday, 01 June 2014
    • Completion Monday, 31 December 2018
    • Location Georgia

    Manpower and Equipment Supply

    Call-Out manpower and equipment supply for South Caucasus Pipeline Expansion Project (“SCPX’) early works and facilities worksites.

    Project Details

    • Client Name ENKA Insaat ve Sanayi A.S.Branch In Georgia
    • Work Type Supply Services
    • Start Thursday, 01 May 2014
    • Completion Wednesday, 31 August 2016
    • Location Georgia

    Provision of Civil Services for BP Georgia

    The services are performed along BTC and WREP Oil Pipelines, SCP Gas Pipeline and at BP’s facilities, including pump stations, pressure reduction stations, PSG1, PSG2, pipelines right of way, valve stations, river crossings, Supsa terminal, storage yards etc.
    The services include - road repair, gravel work, equipment repair, response to land slips and other erosion-related emergencies, remedial works, manual handling, small civil constriction works, mechanical works, provision of laborers, provide and maintain winter access to a set number of block and check valves, provision of materials, equipment, plant and machinery, transportation services for heavy and light loads. The Project is on Call-off basis.

    Project Details

    • Client Name BP Exploration (Caspian Sea) Ltd. - Georgia
    • Work Type Civil Services
    • Start Thursday, 01 May 2014
    • Completion Wednesday, 31 January 2018
    • Location Georgia

    CSG2 Road Camp Construction

    Performance of preparatory works such as: preparation of PCP documentation, design, personnel training, machinery preparation, furnishing, and personnel trainings etc. for CSG2 Road Camp Construction works.
    Worksite preparation in three levelled terraces. Quarry operations and installation of perimeter fencing and all necessary underground services to make the Camp operational. Construction of highway acceleration and deceleration lanes in both directions on the Millennium Highway.
    Installation of the utility distribution systems, such as electrical, telecommunication, fire detection, water, sewage and firefighting.
    Erection of the prefabricated construction camp buildings, facilities and utility plants foundations in accordance with supplier’s instructions and with supplier’s assistance.

    Project Details

    • Client Name BP Exploration (Caspian Sea) Ltd. - Georgia
    • Work Type Design, Construction
    • Start Wednesday, 01 May 2013
    • Completion Monday, 30 June 2014
    • Location Georgia

    Construction of road bridge over r. Oshora

    Topographic, geotechnical and hydrological calculations. Elaboration of detailed design including structural calculations of bridge piers, steel superstructure and roadway reinforced concrete slab. Construction works included earthworks, reinforced concrete works for piers and roadway slab, arrangement of steel superstructure using I-beams, installation of steel railing.

    Project Details

    • Client Name BP Exploration (Caspian Sea) Ltd. - Georgia
    • Work Type Detail design, Construction
    • Start Tuesday, 01 May 2012
    • Completion Monday, 31 December 2012
    • Location Georgia

    Provision of SCP/WREP Civil Survey and Design Works

    The services are performed on Call Off basis in respect of the Company’s Export PL’s - WREP and SCP Georgian sectors with approx. length of 373km (WREP) and 250km (BTC/SCP) extending from the Azerbaijan/Georgian border to Supsa Terminal (WREP) and the Georgian/Turkish border. Survey and detail design included the following, but not limited to: mechanical, structural, piping, corrosion, welding, electrical, safety/fire, automation, telecommunications, erosion control, landslide mitigation and river crossings enhancement.

    Project Details

    • Client Name BP Exploration (Caspian Sea) Ltd. - Georgia
    • Work Type Design, Survey
    • Start Thursday, 01 December 2011
    • Completion Wednesday, 30 April 2014
    • Location Georgia

    Provision of Topographic and CP & Soil Resistivity Surveys for WREP Sectional Replacement Project

    Scope of services included provision of senior surveyor, assistants to surveyors and skilled technician.

    Project Details

    • Client Name RSK Environment Ltd
    • Work Type Topographical Survey
    • Start Monday, 01 August 2011
    • Completion Friday, 30 September 2011
    • Location Georgia

    Design of potable water supply improvement and surface water drainage for the IDP’s settlements in 8 villages

    Provision of topographical works and services, production of situation plans and longitudinal profiles (as a baseline input for engineering design), provision of logistical and administrative services in connection with the above.

    Project Details

    • Client Name Holinger International Consultants GmbH
    • Work Type Topographical Survey
    • Start Friday, 01 July 2011
    • Completion Wednesday, 31 August 2011
    • Location Georgia

    Shamkir River Remediation Work

    Managing QA/QC at the construction site – supervision of excavation, installation of formwork, backfilling and compaction, inspection of concrete at batching plant and on site, application of riprap, reinstatement, material control, warehouse auditing, supervision of preparation of all documents related to quality; managing commissioning system based on Guidance on Certification concept.

    Project Details

    • Client Name BP Exploration (Caspian Sea) Ltd. - Georgia
    • Work Type QA/QC
    • Start Friday, 01 April 2011
    • Completion Wednesday, 30 November 2011
    • Location Azerbaijan

    Provision of BTC/SCP/WREP river crossing rehabilitation works

    Scope of services includes design of protective structures (if necessary) and carry out their construction at river banks and crossings using riprap, gabions, Reno Mattresses and concrete/reinforced concrete structures. Production of relative as-built drawings. The contract is based on Call Offs.
    By December, 2013 IDC Ltd has completed rehabilitation of 28 river crossings, where in total 56,613 m3 of soil were excavated, 33,409 m3 of riprap were arranged, 3,362 m3 of gabions and Reno Mattresses were installed. Total area of the construction works was 26,748 m2.
    Also, 4 landslide areas were rehabilitated with total excavation volume of 7,577 m3 and installation of 4,202 m3 of gabions and Reno Mattresses.

    Project Details

    • Client Name BP Exploration (Caspian Sea) Ltd. - Georgia
    • Work Type Design, Construction
    • Start Friday, 01 April 2011
    • Completion Wednesday, 30 April 2014
    • Location Georgia

    Provision of Topographic and CP & Soil Resistivity Surveys for SCPX Project

    Scope of services included provision of senior surveyor, assistants to surveyors and skilled technician.

    Project Details

    • Client Name RSK Environment Ltd
    • Work Type Topographical Survey
    • Start Friday, 01 April 2011
    • Completion Tuesday, 31 May 2011
    • Location Georgia

    Office Building

    Execution of topographical and geotechnical surveys, detail design of the building, which included all elements of the building, such as structural, mechanical, HVAC, electrical etc.
    Construction of three story office with total area of 900 sq.m. Works included earth works for foundation, installation of foundation slab, columns, beams and ceiling slab with r/c structures, hydro insulation of foundation and ceiling slab, arrangement of walls and partitions with various materials, their plastering and painting, installation of windows and doors, installation of water supply, sewerage and power networks, arrangement of bathrooms and toilets, arrangement of flooring, heating/ventilation/air conditioning, computer and phone networks, window jalousies, provision of office furniture. Pavement of 2,000 m2 yard with reinforced concrete.

    Project Details

    • Client Name IDC Ltd
    • Work Type Design, Construction, Survey
    • Start Friday, 01 October 2010
    • Completion Tuesday, 31 July 2012
    • Location Georgia

    Landslide Movement Monument Survey on AGT & WREP Pipelines in Georgia

    Scope of services includes monitoring topographic survey of SM and DM existing on the landslide sections and faulty zones alongside the AGT Pipelines in Georgia (in Krassovsky 1940 absolute coordinate system). Topographic works are carried out with Total Stations after which new data or Monuments are compared to that of old ones. In total baseline survey of 204 existing monuments should be carried out.
    Scope of services includes monitoring topographic survey of new SM and DM on the landslide sections and faulty zones alongside the AGT & WREP Pipelines in Georgia (in Krassovsky 1940 absolute coordinate system). Topographic works are carried out with Total Stations & GPS after which new data or Monuments are compared to that of old ones. In total baseline survey of 204 existing monuments should be carried out.

    Project Details

    • Client Name BP/BTC Co
    • Work Type Topographical Survey
    • Start Sunday, 01 August 2010
    • Completion Friday, 31 December 2010
    • Location Georgia

    Provision of Engineering Design and Survey Services

    A scope of services includes, but it is not limited to the supply of personnel to perform investigations, discipline and design services supporting projects as directed by COMPANY. Engineering technical discipline include topography, geotechnical, structural, civil, architectural, HVAC, mechanical, electrical.

    Project Details

    • Client Name BP/BTC Co
    • Work Type Design, Survey
    • Start Saturday, 01 May 2010
    • Completion Wednesday, 30 November 2011
    • Location Georgia

    PSG2 Permanent Accommodation Design

    Geotechnical and topographic survey, vertical planning. Design of: drainage for rainwater runoff, hot and cold water distribution system, architectural design including finishes, layout, windows, doors, etc, structural design, concrete roads and pavements per BTC standards.

    Project Details

    • Client Name BP/BTC Co
    • Work Type Design, Survey
    • Start Thursday, 01 April 2010
    • Completion Monday, 28 February 2011
    • Location Georgia

    Preliminary geotechnical and topographical survey in Akhaltsikhe region

    Drilling of boreholes, 60 l.m., geotechnical reconnaissance of research area, topographical survey of approximately 60-hectare area (scale 1:1000), production of report.

    Project Details

    • Client Name ABB
    • Work Type Preliminary Survey, Production of report
    • Start Monday, 01 March 2010
    • Completion Wednesday, 31 March 2010
    • Location Georgia

    Design/construction of “Beeline” towers

    Drilling one borehole (with depth of 5-10 m) at each site of tower installation; taking soil and water samples from the boreholes and performance of their laboratory analysis; preparation of geotechnical report (geotechnical investigations for installation areas of 56 towers has been performed up to date); inspection of tower foundation design provided by the client and performance of expert examination; supervision of arrangement of tower foundation and tower installation works during construction activities; laboratory testing of concrete test cubes, inspection of tower verticality, inspection of certification of the materials

    Project Details

    • Client Name “Coliseum Group” Ltd
    • Work Type Geotechnical Survey, Supervision, expert examination
    • Start Monday, 01 February 2010
    • Completion Sunday, 30 September 2012
    • Location Georgia

    Supervision for Upgrading Vaziani-Gombori-Telavi Road

    Supervision for upgrading Km 0 - -Km 27 and Km 27 – Km 54 section of Vaziani-Gombori-Telavi Road.
    IDC Ltd acted as a “Local Associate” of MMM Group limited (“Lead Consultant”). Works were conducted in accordance of FIDIC guidelines and included supervision of: road rehabilitation, arrangement of bridges, gabions, retaining walls, water drainage and reinforced concrete channels.

    Project Details

    • Client Name MMM Group
    • Work Type Supervision
    • Start Friday, 01 January 2010
    • Completion Saturday, 30 June 2012
    • Location Georgia

    Geotechnical investigation and civil design for installation of STP at Supsa Terminal

    Topographical and geotechnical surveys were performed. Reinforced concrete foundations for STP units (RBC Unit, Twin Effluent Pump Station, UV Chamber and Mag Flow meter), concrete surroundings and pipelines from STP facilities to r. Supsa were designed in accordance with provided dimensions. Layout schemes for STP facilities were determined.

    Project Details

    • Client Name BP/BTC Co
    • Work Type Design, Survey
    • Start Friday, 01 January 2010
    • Completion Sunday, 31 January 2010
    • Location Georgia

    Provision of Plot Plans at PSG1 and PSG2 and Geodesic works

    Provision of topographic works in order to construct accommodation facilities in Gardabani PSG1 and Tetritskaro PSG2, determination of ground volumes needed to cut out(excavate) and scatter. Determination of layout of accommodation facilities and utilities needed to be directed towards them.

    Project Details

    • Client Name BP/BTC Co
    • Work Type Design, Survey
    • Start Sunday, 01 November 2009
    • Completion Sunday, 31 January 2010
    • Location Georgia

    Designing of measures for protection of BTC/SCP and WREP Pipelines from washout at the river Shamkirchai, Azerbaijan

    Temporary measures, for protection of Pipelines from washout, have been designed at the river Shamkirchai and permanent measures are in the stage of designing. Designing includes arrangement of concrete and riprap barrages, arrangement of river bed revetment structures by means of riprap.

    Project Details

    • Client Name BP Exploration (Caspian Sea) Ltd. - Georgia
    • Work Type Detail design
    • Start Thursday, 01 October 2009
    • Completion Wednesday, 31 March 2010
    • Location Azerbaijan

    Provision of Back-up Civil Services

    Conducted works comprise the following:
    - Arrangement of Wind Turbine Foundations and Cable Ducts at Block Valves 03 and 16 of BTC Pipeline.
    - Fence Repair Works at Block Valves 15 and 16 of BTC Pipeline.
    - Arrangement of Reinforced Concrete Trackways for Turbine Removal at PSG 1 and PSG 2.
    Works include detailed design as well as construction.

    Project Details

    • Client Name BP/BTC Co
    • Work Type Detail design, Construction
    • Start Tuesday, 01 September 2009
    • Completion Sunday, 31 January 2010
    • Location Georgia

    Area 80 PA Construction

    Works consist of:
    - Earth works, ditch arrangement around the site, area fencing, internal road arrangement, concrete sidewalk arrangement, area landscaping.
    - Bedroom facility/connecting hallway and kitchen-dining facility construction (with total area 1020,8 sq.m.). These activities included construction of the foundation, foundation slab, columns, beams and ceiling slab with the r/c structures; also, arrangement of walls and partitions with various materials, their plastering and painting, winterization (warmth-keeping) of the foundation. Arrangement of steel trusses and purlins, roofing of buildings with galvalume-coated metal materials. Buildings were furnished with metal plastic windows, metal doors, iron-framed wooden doors, metal plastic doors and etc. Arrangement of indoor electrical system; outdoor security lighting, water supply, sewer system, heating, ventilation, security CCTV system, fire alarm system.
    - Generator and fuel storage shelter construction
    - Arrangement of chiller/freezer shelter
    - Arrangement of STP and its respective reed-bed.

    Project Details

    • Client Name BP/BTC Co
    • Work Type Construction
    • Start Tuesday, 01 September 2009
    • Completion Sunday, 28 February 2010
    • Location Georgia

    Arrangement of magnets alongside the BTC and SCP Pipelines

    Works included arrangement of magnets at the top of the pipelines and their planning in absolute coordinates. In total 38 magnets have been arranged. Besides this, temporary monuments have been arranged alongside the pipelines.

    Project Details

    • Client Name BP/BTC Co
    • Work Type Survey
    • Start Saturday, 01 August 2009
    • Completion Wednesday, 30 September 2009
    • Location Georgia

    Arrangement of gabions on Secondary Containment Structures in Bakuriani and provision of reinforced concrete works.

    In Bakuriani region, pouring of reinforced concrete on the parapets of Secondary Containment Structures arranged on the rivers: Tskhratskaro, Kumiska-1, Kumiska-2, Oshora-1 and Oshora-2 and in the foundations of three generators (356m³). Construction of storage places for three generators; provision of facing works in them.
    Arrangement of 7343m³ gabions at the banks of the aforementioned rivers.

    Project Details

    • Client Name BP/BTC Co
    • Work Type Construction
    • Start Wednesday, 01 July 2009
    • Completion Sunday, 31 January 2010
    • Location Georgia

    Arrangement of foundations for wind turbines and cable ducts at BV16 and GB03

    For installation of four wind turbines at BV16 and GB03 following works were done - topographical survey and geotechnical investigations of sites, calculation of bearing capacities of turbine foundations, rehabilitation of access roads, preparation of construction sites, installation of foundations of turbines and winch anchors with reinforced concrete, installation of cable ducts.

    Project Details

    • Client Name BP/BTC Co
    • Work Type Design, Construction, Survey
    • Start Wednesday, 01 July 2009
    • Completion Saturday, 31 October 2009
    • Location Georgia

    Arrangement of monuments alongside the BTC and SCP Pipelines

    Works included arrangement of monuments alongside the pipelines and their planning in absolute coordinates. In total 203 monuments have been arranged.

    Project Details

    • Client Name BP/BTC Co
    • Work Type Survey
    • Start Wednesday, 01 July 2009
    • Completion Saturday, 31 October 2009
    • Location Georgia

    Designing and construction of STP facilities in Tetritskaro (PSG2) and Tsalka (OSRB).

    Topographical and geotechnical surveys have been conducted; there have been designed reinforced concrete foundations for STP facilities and concrete surroundings, reinforced concrete intake and discharge manholes in the reed-bed according to the given dimensions, also pipelines from STP facilities to the reed-bed and from the reed-bed to the existing ravine. Layout schemes for STP facilities have been determined. Construction process included installation of necessary STP equipment (RBC Unit, Twin Effluent Pump Station, UV Chamber and Mag Flow meter) on the pre-arranged reinforced concrete foundation and placement of these equipment in the concrete slabs. Also, construction of reed-bed.

    Project Details

    • Client Name BP/BTC Co
    • Work Type Detail design, Construction, Survey
    • Start Sunday, 01 March 2009
    • Completion Thursday, 31 December 2009
    • Location Georgia

    Fortification of river Supsa, Tkhilnara and Kvintskali crossings of the WREP Pipeline

    Beds of all three rivers and their banks were fortified by means of 0, 7-1,0m size riprap. In total, 1400mі of riprap have been arranged on all three rivers.

    Project Details

    • Client Name BP/BTC Co
    • Work Type Construction
    • Start Sunday, 01 March 2009
    • Completion Tuesday, 30 June 2009
    • Location Georgia

    Area 80 Permanent Accommodation Design

    Area topographical survey and geotechnical investigation. Permanent Accommodation Area consist of the following facilities: bedroom facility for 24 persons, kitchen/dining facility, guard house, generator enclosure and fuel storage shed, sewage treatment plant, smoking shelter, waste segregation area, outdoor recreation area, parking area, court. The work included the following designs: area vertical planning architectural, structural, indoor electrical system; outdoor security lighting, water supply, sewer system, heating, ventilation, security CCTV system, fire alarm system etc. For the design were applied local standards as well as British Standards, IBC-2000, NFPA 101.

    Project Details

    • Client Name BP/BTC Co
    • Work Type Detail design
    • Start Sunday, 01 March 2009
    • Completion Saturday, 31 October 2009
    • Location Georgia

    Geotechnical surveys for four administration buildings of Tbilisi city

    Geotechnical survey included study of location places of administration buildings in the four districts of Tbilisi. Drilling works and laboratory analysis have been conducted resting on them geotechnical conclusions, for all four building locations, have been issued.

    Project Details

    • Client Name Tbilisi City Council
    • Work Type Geotechnical Survey
    • Start Monday, 02 February 2009
    • Completion Tuesday, 30 June 2009
    • Location Georgia

    Rectification Work at WREP Liakhvi River Crossing

    In order to enhance the integrity of the Western Route Export Pipeline crossing, emergency repair was carried out. Up to 3 000 cub.m. Riprap was placed alongside Liakhvi river crossing with the pipeline. As built documentation preparation.

    Project Details

    • Client Name BP/BTC Co
    • Work Type Construction
    • Start Thursday, 01 January 2009
    • Completion Saturday, 28 February 2009
    • Location Georgia

    R. Satskhenisi WREP Crossing Topographical Survey

    Topographic Survey of WREP Satskhenisi river crossing corridor (width 20m) and determining pipeline depth. Desktop processing of the filed data.

    Project Details

    • Client Name BP/BTC Co
    • Work Type Topographical Survey
    • Start Thursday, 01 January 2009
    • Completion Saturday, 28 February 2009
    • Location Georgia

    Geotechnical Survey on the Territory of Tbilisi Tuberculosis Center

    Drilling of 4 boreholes (19m of total length) within Tbilisi Tuberculosis Center, soil laboratory testing, drafting geotechnical report.

    Project Details

    • Client Name Caucasus Consulting Group
    • Work Type Geotechnical Survey
    • Start Thursday, 01 January 2009
    • Completion Saturday, 31 January 2009
    • Location Georgia

    Containers Strengthening at PSG1

    Fixing 36 office containers with special steel elements on the pre-arranged concrete blocks.

    Project Details

    • Client Name BP/BTC Co
    • Work Type Design, Construction
    • Start Wednesday, 01 October 2008
    • Completion Sunday, 30 November 2008
    • Location Georgia

    Construction of Shelter for Generators at South Caucasus Pipeline Area 80

    Design and Construction reinforced concrete foundations of the shelter for generators at SCP Area 80.

    Project Details

    • Client Name CMB Developments LTD
    • Work Type Design, Construction
    • Start Wednesday, 01 October 2008
    • Completion Wednesday, 31 December 2008
    • Location Georgia
    Page 1 of 3
    © 2002-2019 IDC Ltd. All Rights Reserved. Developed By GT-studio

    Search