The works include servicing, maintenance, testing/verification, repairing, asset registry, providing asset identification tags and where required re-placement, of infrastructure, buildings, services and equipment of Baku-Supsa and Baku-Tbilisi-Ceyhan oil pipelines and South Caucasus Gas Pipeline.
This shall include without limitation to: Buildings, Physical Security installations and high pole perimeter lights, Roads, paving’s, walkways and hard standings within perimeter fencing of worksites, All lighting and illumination fixtures and fittings, Television system, including required cable TV licenses, hardware, Set Top Boxes, Recreational facilities, Mechanical installations, Electrical Installations including primary power generation and distribution, Fire and life safe systems and modules, including appliances, Voice and data systems, All graded and paved roads inside the worksites, Security systems including fences and other ancillary equipment, Installed capital equipment including but not limited to Power Generators, Power Distribution, Potable Water, Sewage Treatment, Site Drainage System, HVAC, Hot & Cold Water, Automatic Fire Detection System, and Firewater System (excludes Security Systems). catering and laundry equipment, traffic management systems, and the like.
Civil works - temporary works, site clearance, site set-up, transportation (including handling and lifting) from warehouse or fabrication yard to work site of materials (permanent and temporary) and equipment, in-situ concrete, pre-cast concrete, piling, excavations, shoring, fencing, man-holes, pits/covered tanks, sewer and water main renovation and ancillary works, pipelines and pipework (on ground, in trenches), roads and pavings, earthworks, ground investigation, building works, reinstatement, drainage works, dewatering, cable ducting (below ground), procurement, supply and delivery of some permanent materials such as reinforcing steel, concrete, ducting, grating, procurement, supply and delivery of consumables, painting, waterproofing, inspection and testing, removal of excess and waste materials from the worksite upon completion of the work, participation in constructability reviews, participation in risk review sessions and preparation of risk assessments, preparation of as-built and materials traceability drawings, weld record/NDE drawings and the compilation and presentation of certification packages.
Structural works - structural fabrication, pre-fabrication, transportation (including handling and lifting) from warehouse or fabrication yard to work site of prefabricated assemblies, materials, and equipment, structural construction, procurement, supply and delivery of consumables, Inspection and testing, removal of excess and waste materials from the worksite upon completion of the work, participation in constructability reviews, participation in risk review sessions and preparation of risk assessments, preparation of as-built and materials traceability drawings, weld record/NDE drawings and the compilation and presentation of certification packages.
The Project is on Call-off basis.
Civil works - temporary works, site clearance, site set-up, transportation (including handling and lifting) of materials and equipment, in-situ concrete, pre-cast concrete, piling, excavations, shoring, fencing, man-holes, pits/covered tanks, sewer and water main renovation and ancillary works, pipelines and pipework (on ground, in trenches), roads and pavings, earthworks, ground investigation, building works, reinstatement, river crossings works, drainage works, dewatering, cable ducting (below ground), procurement, supply and delivery of materials and consumables, painting , waterproofing, inspection and testing, removal of excess and waste materials from the worksite upon completion of the work., preparation of as-built and materials traceability drawings, weld record/NDE drawings and the compilation and presentation of certification packages.
Structural works - structural fabrication, pre-fabrication, transportation (including handling and lifting) of pre-fabricated assemblies, materials and equipment, structural construction, procurement, supply and delivery of consumables, inspection and testing, removal of excess and waste materials from the worksite upon completion of the work, preparation of as-built and materials traceability drawings, weld record/NDE drawings and the compilation and presentation of certification packages.
The Project is on Call-off basis.