Modification/upgrade of existing 1000 m long drainage ditch along Millennium Road with positioning of the mass concrete weirs.
Topographical survey of approximate 7-hectare area, execution of CBR testing, issue of respective topographical drawings and geotechnical report.
Design of rehabilitation measures of Liakhvi river crossing, site preparation, 68 868 m3 soil excavation, 15 000 m2 geotextile filter layer installation, 19 043 m3 riprap installation to armour the river banks, 21 320 m3 riprap installation for arrangement of threshold across the river bed, 24 290 m3 excavated soil backfill and installation of fill, installation of dam with 2 810 m3 local sand/gravel, distribution of 40 374 m3 surplus soil within the river bed and at riverside slopes, supply and delivery of 34 460 m3 of stones, site reinstatement, preparation of as-built drawings.
Detail Design for all disciplines required for the Services including, but not limited to: mechanical, structural, piping, stress, process, corrosion, welding, instrumentation, electrical, safety/fire, automation, telecommunications, materials, package/vendor, civil including erosion control, landslide mitigation and river crossings enhancement works engineering. The Project is on Call-off basis.
Erosion control and reinstatement works at River Crossings, which includes but not limited to river bank and bed reinforcement works with Riprap, Maccaferri gabions, concrete structures and etc; Reinstatement and recovery of the preconstruction vegetation and etc. The Project is on Call-off basis.
Provide Company with construction, civil engineering, design, surveying and general Project services as per detailed Scope of Work described in Call-Off’s, which shall be issued by Company time by time. The works performed / to be performed at any site/s required by Company inclusive of, but not limited to, pipeline river and canal crossings, access roads, pipeline over-ground installations etc.
Call-Out manpower and equipment supply for South Caucasus Pipeline Expansion Project (“SCPX’) early works and facilities worksites.
The services are performed along BTC and WREP Oil Pipelines, SCP Gas Pipeline and at BP’s facilities, including pump stations, pressure reduction stations, PSG1, PSG2, pipelines right of way, valve stations, river crossings, Supsa terminal, storage yards etc.
The services include - road repair, gravel work, equipment repair, response to land slips and other erosion-related emergencies, remedial works, manual handling, small civil constriction works, mechanical works, provision of laborers, provide and maintain winter access to a set number of block and check valves, provision of materials, equipment, plant and machinery, transportation services for heavy and light loads. The Project is on Call-off basis.
Topographic, geotechnical and hydrological calculations. Elaboration of detailed design including structural calculations of bridge piers, steel superstructure and roadway reinforced concrete slab. Construction works included earthworks, reinforced concrete works for piers and roadway slab, arrangement of steel superstructure using I-beams, installation of steel railing.
Scope of services included provision of senior surveyor, assistants to surveyors and skilled technician.