Design works in order to improve pipeline operable conditions at KP479,7 from Baku tectonic fault crossing of Georgian Section of WREP.
Design works: F5,3 ha field topographic survey, geotechnical and laboratory works, pipeline burial depth determination, desktop processing, development of the design to provide re-grading of soil cover on the 200m section of the pipeline also to enable effective drainage of rainwater by rip-rap channels; determination of relevant ground works scopes; reduce soil cover to 0.9m over the pipeline in order to improve pipe working under seismic loads