Shamkir River Remediation Work

Client
BP Exploration
Work Type
QA / QC
Location
Azerbaijan
Project Status
Completed
Start Date
2011-04-27
End Date
2011-11-27
Shamkir River Remediation Work
Managing QA/QC at the construction site – supervision of excavation, installation of formwork, backfilling and compaction, inspection of concrete at batching plant and on site, application of riprap, reinstatement, material control, warehouse auditing, supervision of preparation of all documents related to quality; managing commissioning system based on Guidance on Certification concept.