GB21 Access Road Detailed Design

Survey / Design

GB21 Access Road Detailed Design

Client
BP/BTC Co
Work Type
Survey / Design
Location
Georgia
Project Status
Completed
Start Date
2006-06-27
End Date
2006-07-27

GB21 Access Road Detailed Design

Detail design of 2.2km long access road to GB21. For narrowing the gradients and selecting best road cover, three options were developed. Among the developed options, option II was considered most feasible, in case of which maximum gradient did not exceed 22%, which ensured more safe movement compared to option I and III.

Looking to Execute a Similar Project?

Partner with IDC to bring your next infrastructure, energy, or industrial project to life. With decades of proven experience and a commitment to quality, safety, and precision, we're ready to help you achieve outstanding results.

Get in touch
Investigation | Design | Construction | Supervision