Fortification of river Supsa, Tkhilnara and Kvintskali crossings of the WREP Pipeline.

Client
BP/BTC Co
Work Type
Construction
Location
Georgia
Project Status
Completed
Start Date
2009-03-27
End Date
2009-06-27
Fortification of river Supsa, Tkhilnara and Kvintskali crossings of the WREP Pipeline.
Beds of all three rivers and their banks were fortified by means of 0, 7-1,0m size riprap. In total, 1400m³ of riprap have been arranged on all three rivers.