Rustavi-Jandara Road Rehabilitation, Section 2 (6,0 km length)

Client
BP Exploration
Work Type
Construction
Location
Georgia
Project Status
Completed
Start Date
2017-11-27
End Date
2018-01-27
Rustavi-Jandara Road Rehabilitation, Section 2 (6,0 km length)
Project planning and scheduling, monitoring and reporting of physical and financial progress, quality assurance, HSE assurance, procurement. Carry out construction works such as - excavation of damaged asphalt concrete, constructing of road base with sand-crushed stone material, arrangement layers of pavement from coarse and fine-grained asphalt concrete mix.