PAT E1 Gas Pipeline Detail Design

Processing route options and selection of final route; provision of topographical, geotechnical and hydrological surveys; elaboration of pipeline plan and profile, plan of crossings, typical drawings, work scopes, MTO, calendar schedule and organization chart of construction works. Obtainment of construction permit. Length of gas pipeline is 19.6 km.

Project Details

  • Client Name: Schlumberger Rustaveli Company Limited (Branch) – Georgia
  • Work Type: Design, Survey
  • Start: December 2018
  • Completion: July 2019
  • Location: Georgia