    Monday, 30 October 2017 19:04

    Maintenance Works at Rustavi Pipe Yard

    Installation of Electrical Lighting, Installation and Dismantling of a Portable Toilet, Rent of Generator, Security Shack, Changing Room

    Project Details

    • Client Name Seacor Environmental Services International
    • Work Type Maintenance
    • Start February 2005
    • Completion May 2005
    • Location Georgia
    Published in Projects

    Installation of six monitoring boreholes and piezometers for continuous monitoring of underground water levels on river Mtkvari.

    Project Details

    • Client Name BP/BTC Co
    • Work Type Field Survey
    • Start February 2005
    • Completion March 2005
    • Location Georgia
    Published in Projects

    Topographic survey of Kura river downstream of crossing site at KP 223 using Total Station equipment for design of village protection works.

    Project Details

    • Client Name BP/BTC Co
    • Work Type Field Survey, Drawings Development
    • Start February 2005
    • Completion February 2005
    • Location Georgia
    Published in Projects

    Topographic survey of Kura West River crossing, Obtaining hydrological data for Kura East River crossing.

    Project Details

    • Client Name BP/BTC Co
    • Work Type Field Survey, Report Development
    • Start February 2005
    • Completion February 2005
    • Location Georgia
    Published in Projects

    Drilling boreholes and arrangement of piezometers for underground water encountering and water level monitoring purposes. Taking water and soil samples and carry out lab analysis, arrangement of monuments for monitoring the land-slide area.

    Project Details

    • Client Name BP/BTC Co
    • Work Type Field Survey, Report Development
    • Start January 2005
    • Completion January 2005
    • Location Georgia
    Published in Projects

    Spatial modelling of building carcass on cross and long seismic forces using program Lira, determination of the strength of earthquake the existing building shall resist, design of constructive measures to increase the building seismicity, calculation of the floor of the building on loads caused by transport movement.

    Project Details

    • Client Name BP/BTC Co
    • Work Type Field Survey, Structural Study
    • Start December 2004
    • Completion March 2005
    • Location Georgia
    Published in Projects

    Hydrological survey, hydraulic calculation of structures, structures bearing constructions design, access road design, and construction works scopes and schedules determination, construction works cost estimation.

    Project Details

    • Client Name BP/BTC Co
    • Work Type Field Works, Detail design
    • Start December 2004
    • Completion February 2005
    • Location Georgia
    Published in Projects
    Monday, 30 October 2017 15:59

    Pipeline Construction Support Services

    Trench line safety barrier construction, damage repair to essential services or structures, area clean-up and row clean-up, Akhaltsikhe and Tsalka Camps maintenance works, BV17, BV18, BV21 and BV22 maintenance works

    Project Details

    • Client Name BP/BTC Co
    • Work Type Maintenance
    • Start October 2004
    • Completion March 2005
    • Location Georgia
    Published in Projects